If you need planning permission for an HMO, a valid application made on or before 7 December 2026 costs £610; from 8 December 2026 it costs £732. That is the material change of use fee for a C3 to C4 conversion inside an Article 4 area and for any large HMO of 7 or more. A lawful development certificate for an existing HMO use costs the same; a proposed-use certificate half. The rises are set nationally in SI 2026/1192, made on 10 November 2026 and in force on 8 December 2026.
Who pays the change of use fee
Where a council's Article 4 direction has removed the permitted development right, turning a family home into a small HMO (3 to 6 people) is a material change of use and needs a full application at the category 14 fee. See HMO Article 4 by council.
£610 to £732An HMO for 7 or more people is sui generis everywhere in England, so it always needs permission for the change of use: the same category 14 fee, Article 4 or not.
£610 to £732Proving an existing HMO use is lawful costs the full application fee; a certificate for a proposed use costs half. Both move with the category 14 figure.
£610 or £305 nowBefore and after, every fee that touches a landlord
| Application | From 1 April 2026 | From 8 December 2026 | Change | Unit |
|---|---|---|---|---|
| HMOs and changes of use | ||||
| Material change of use (category 14): C3 house to C4 small HMO in an Article 4 area, or any large HMO of 7 or more (sui generis) | £610 | £732 | +20% | per application |
| Lawful development certificate, existing use (for example an HMO already in use): same as the full application fee The schedule sets this as 'Same as Full Application fee'; the figures are the category 14 fee. | £610 | £732 | +20% | per application |
| Lawful development certificate, proposed use: half the full application fee 'Half the Full Application fee'; the figures are half the category 14 fee. | £305 | £366 | +20% | per application |
| Change of use to separate dwellings, fewer than 10 (category 12): house to flats Where a single house becomes two or more dwellings the fee is per additional dwelling; in other cases per dwelling. 10 to 49 dwellings: £659 to £799 each. | £610 | £700 | +14.8% | per additional dwelling |
| Householder works | ||||
| Alteration or extension of a single house (category 6) | £548 | £575 | +4.9% | per application |
| Alteration or extension of two or more houses (category 6) | £1,083 | £1,130 | +4.3% | per application |
| Works within the curtilage: outbuildings, fences, walls (category 7) | £272 | £285 | +4.8% | per application |
| Conditions and amendments | ||||
| Vary or remove a condition (section 73), householder | £89 | £112 | +25.8% | per application |
| Vary or remove a condition (section 73), major development | £2,076 | £3,150 | +51.7% | per application |
| Vary or remove a condition (section 73), any other case | £608 | £608 | no change | per application |
| Discharge of conditions, householder | £89 | £125 | +40.4% | per request |
| Discharge of conditions, any other case | £309 | £435 | +40.8% | per request |
| Non-material amendment, householder | £46 | £53 | +15.2% | per application |
| Non-material amendment, any other case | £309 | £360 | +16.5% | per application |
| Certificate that it is lawful not to comply with a condition | £309 | £360 | +16.5% | per application |
| Reserved matters where the full application fee was already paid | £610 | £749 | +22.8% | per application |
| Prior approval | ||||
| Prior approval, householder: larger rear extension (Part 1 Class A) or upward extension (Class AA) | £249 | £310 | +24.5% | per application |
| Prior approval, commercial to residential (Part 3 Class MA) | £260 | £323 | +24.2% | per proposed dwelling |
| Prior approval, other buildings to dwellings (Part 3 Classes M, N, Q) | £249 | £310 | +24.5% | per application |
| Prior approval, Classes M, N, Q with building operations | £536 | £667 | +24.4% | per application |
| All other applications for prior approval | £249 | £310 | +24.5% | per application |
Current fees from MHCLG's 1 April 2026 schedule; 8 December fees checked against SI 2026/1192 on 13 November 2026 (the provision for each row is in SOURCES.txt); percentages are our arithmetic. A flat £310 fee is introduced for certain prior approval applications that previously had no fee (regulation 4(i) of SI 2026/1192, inserting regulation 14(1)(d) into the 2012 Regulations: 'for any other application under that Schedule, £310'). Some early commentary says the householder prior approval fee (larger rear extensions, upward extensions) is new. The 1 April 2026 schedule already lists it at £249; from 8 December it is £310.
What to do before 8 December 2026
The regulations: SI 2026/1192, made 10 November 2026
The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026, SI 2026/1192. Made 10 November 2026 after a draft was approved by resolution of each House; published on legislation.gov.uk 13 November 2026. Regulation 1(2): "These Regulations come into force on 8th December 2026." Regulation 12(1): The amendments made by regulations 3 to 11 do not apply to (a) any application made before the commencement date, or deemed to have been made in connection with an enforcement notice issued before the commencement date, (b) any request made before the commencement date, or (c) any site visit which takes place before the commencement date. Regulation 12(2) moves the annual indexation 'fee change date' in regulation 18A of the 2012 Regulations to 1st April 2027.
The instrument amends the un-indexed base text of the 2012 Regulations, so the amounts it replaces (for example £298 in regulation 16(1)(b)) are lower than the current indexed fee on MHCLG's table (£309). The 'before' column on this page is the current indexed fee from MHCLG's 1 April 2026 schedule; the 'from 8 December' column is the amount written in the instrument. The 3.5% indexation on 1 April 2027 is MHCLG's stated figure: the instrument sets the date (regulation 12(2)), not the percentage. Read the instrument.
Questions
Which fee does an HMO conversion pay?
A material change of use, category 14 of the fee schedule: £610 now and £732 from 8 December 2026. That covers a family home (C3) to a small HMO (C4) where an Article 4 direction has removed permitted development, and any large HMO of 7 or more people (sui generis), which always needs permission. Where no Article 4 applies, a C3 to C4 change is permitted development and there is no fee.
Do applications already in by 7 December pay the old fee?
Yes, under regulation 12(1) of SI 2026/1192: the new fees "do not apply to any application made before the commencement date", and the commencement date in regulation 1(2) is 8 December 2026. An application is made when it is valid, not when it is drafted or when a pre-application enquiry goes in, so check the council's validation checklist and pay the fee in time.
Is this definitely happening?
Yes. The regulations were made on 10 November 2026 after a draft was approved by both Houses of Parliament, were published on legislation.gov.uk on 13 November 2026 as SI 2026/1192, and come into force on 8 December 2026 (regulation 1(2)). Every 8 December figure on this page was checked against the instrument's text on 13 November 2026; the provision for each is in SOURCES.txt.
What happens on 1 April 2027?
The new fees are indexed by 3.5% from 1 April 2027 (the 3.5% is MHCLG's stated figure in its schedule; regulation 12(2) of SI 2026/1192 moves the annual fee change date to that day but sets no percentage). We have not published April 2027 figures as fees; the calculator shows an estimate, labelled as our arithmetic, when you choose that date.
What about lawful development certificates?
The schedule keeps the rule: an existing use certificate costs the same as the full application fee (so £610 rising to £732 for an HMO use), a proposed use certificate half of it (£305 rising to £366).
Does this apply in Wales or Scotland?
No. The regulations extend to England and Wales but amend the England fee regulations only; Wales, Scotland and Northern Ireland set their own planning fees. Kerbio's Welsh council pages do not carry the fee line.
Is this advice?
No. It is what the two MHCLG schedules and SI 2026/1192 say, with the arithmetic shown. Fees are set nationally; councils do not vary them. Confirm the fee with the council's planning portal when you apply.
About this guide
Written by Kerbio, a small independent UK tool for property investors, on 13 November 2026 from the two MHCLG fee schedules and SI 2026/1192. Every fee is in the schedules and the instrument; the percentages are ours. Not legal advice.
Kerbio is a Chrome extension that puts Article 4, licensing, the council's HMO register and sold prices on the listing you are reading.
See the extension
Sources
- The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026, SI 2026/1192, made 10 November 2026 (legislation.gov.uk); contents
- Planning application fees (MHCLG guidance page, updated 10 November 2026)
- Planning fees: national increases from 8 December 2026 (PDF)
- Planning fees: annual indexation from 1 April 2026 (PDF)
Checked 13 November 2026. Quotations and figures in SOURCES.txt. General information, not legal advice. England only.
Kerbio