When each repair step would be due: Awaab's Law deadline calculator

When a tenant reports a hazard, when would each step be due under the rules MHCLG is consulting on for private landlords? Working days and England bank holidays handled. Proposed, not law.

The report

Consultation, not law. Default figures are the social-sector rules, the "in line with social housing" option; the other sets are the shorter and longer options in the consultation (closes 18 December 2026). Nothing applies to private tenancies yet.

Day zero is the day you became aware. Working days exclude weekends, Christmas Day, Good Friday and England bank holidays (loaded to the end of 2028). Leave the conclusion date blank to assume the investigation takes its full period.

Deadlines under the chosen option

Illustration of a live consultation, not legal advice. Source beside each line: the consultation question that sets the option, or the social-sector regulations. What Awaab's Law would mean for private landlords.

How the clock works

Day zero

The day you become aware of a potential hazard, from any source. The investigation period starts the next day.

From the conclusion

Written summary, make-safe and follow-up deadlines all run from the day the investigation concludes, so investigating early brings everything forward.

Emergencies

Investigate and make safe within the hours option, in parallel if needed, then the normal follow-up clock from the day it concluded.

Questions

Are these deadlines law for private landlords?

No. They are the options in MHCLG's consultation, which closes on 18 December 2026. The default here is the set marked "in line with social housing requirements", which is the law for social landlords in England; the shorter and longer sets are the other options the consultation lists. Nothing applies to a private tenancy until regulations are made, which the document says cannot be before 2027.

How are working days counted?

As the social-sector regulations define them: not Saturdays, Sundays, Christmas Day, Good Friday or bank holidays in England. The day you become aware is day zero and the deadline is the end of the last working day. After an investigation, day one is the day after it concludes. Bank holidays are loaded to the end of 2028.

Why does the written summary date depend on when I finish investigating?

Because the summary, make-safe and follow-up clocks all run from the day the investigation concludes, not from its deadline. Enter the date you concluded it and the later deadlines move with it. Leave it blank and the calculator assumes you used the whole investigation period, the latest possible dates.

What counts as an emergency?

In the social-sector regulations an emergency hazard poses an imminent and significant risk of harm to an occupier's health or safety; a significant hazard is one a reasonable landlord would make safe as a matter of urgency but not within 24 hours. The consultation asks whether private tenancies should have a separate emergency timescale at all.

Can I switch this to the final rules later?

That is how it is built: every number comes from one data file. When regulations are made we replace the file and the calculator, the guide and the worked example all change together.

Other free tools

Sources: the consultation document and the social-sector regulations and guidance, listed in the guide and its SOURCES.txt. Checked 2 November 2026.